Mühleberg Nuclear Power Plant - Decision on upgrade of nuclear power plant will only be possible by late 2013

Bern (ots)

BKW is undertaking additional investigations to safeguard the longterm operation of the Mühleberg nuclear power plant (KKM). This is necessary since the initial indicative tenders show that the original estimated costs of 170 million CHF will be exceeded. An assessment of economic viability and a decision on the Mühleberg upgrade projects are planned by the end of 2013. BKW has informed the Bern government about the new situation.

BKW is now working on a new implementation plan based on the initial indicative tenders for the safety-related upgrade work required at the Mühleberg plant. The tenders first need to be carefully analysed. This will involve determining, in consultation with external experts and the safety authorities, whether the proposed measures for which tenders have been made are necessary and sufficient. Moreover, due to lack of competition among the suppliers, careful investigations regarding price fixing need to be undertaken before the results of the economic viability audit and the application for execution of the work can be submitted to the Board.

In its original schedule, BKW assumed that the essential information would be available by mid-2013 for the Board to make a decision. The situation with tenders now appears to be significantly more complex. Furthermore, the period for which the upgrade needs to be planned, and which authorities will be responsible for the final assessment will only become clear after the decision of the Federal Court on the time limit for the operating permit for KKM. The decision process has therefore been delayed by at least six months until the end of 2013. BKW has informed the Governing Council of the Canton of Bern and the regulatory authorities directly about this situation.

Contact:

Antonio Sommavilla, Tel. no: +41 79 743 96 01

Weitere Storys: BKW Energie AG
Weitere Storys: BKW Energie AG
  • 07.12.2012 – 17:30

    Networks: Transfer of transmission grid to swissgrid

    Bern (ots) - BKW Inc. has approved the agreement governing the transfer of the trans-mission grid to swissgrid. BKW will therefore transfer ownership of its transmission grid to swissgrid on 3 January 2013. Back in 2009 BKW, along with other transmission grid owners, began working with swissgrid, the national grid company, on preparations for this transaction as prescribed by law. The contractual and operational ...

  • 23.11.2012 – 17:30

    Finance: Successful borrowing in Euro zone

    Bern (ots) - On 23 November 2012 BKW Inc. placed for the first time two registered notes with terms of 15 and 20 years and for nominal amounts of EUR 40 million and EUR 85 million, respectively. The registered notes are debentures under German law and were placed in Germany. The successful raising of credit on the German capital market secures the currency- and country-matched funding of BKW's investments in Germany and ...

  • 06.11.2012 – 09:53

    Mühleberg nuclear power plant: 40 years of reliable electricity production

    Bern (ots) - Since it was first commissioned in early November 1972, Mühleberg nuclear power plant (KKM), owned by BKW AG, has produced more than 108 billion kilowatt hours (kWh) of electricity reliably and cost-effectively. This corresponds to almost twice the volume of electricity consumed annually by the whole of Switzerland. Successful operation coupled with the ...