Alle Storys
Folgen
Keine Story von BKW Energie AG mehr verpassen.

BKW Energie AG

Mühleberg nuclear power plant
Scheduled annual revision work begins

Bern (ots)

BKW AG yesterday shut down Mühleberg nuclear power plant (MPP) as scheduled to enable annual revision work and refuelling to take place. This revision work is set to last nearly four weeks.

Key aspects of the 2013 annual revision will be extensive repeat testing and inspections of the interior and exterior of the reactor pressure vessel, performed using qualified testing systems. As well, revisions and testing work will be carried out on security systems, turbines and generators, electrical protection and control systems, as well as on transformers. As part of the preventive maintenance, one generator will be examined and six of the 57 control rod drives will be replaced.

Moreover, pipeline weld seams and the core shroud will be inspected with the use of ultrasound test systems. This year, 36 of the 240 fuel elements will be replaced. During the annual overhaul, 340 BKW employees will be assisted by 700 external specialists from the region, from Switzerland and from abroad.

Contact:

antonio.sommavilla@bkw.ch; tel.no: 058 477 51 07

Weitere Storys: BKW Energie AG
Weitere Storys: BKW Energie AG
  • 17.07.2013 – 07:00

    BKW Inc. 2012 Sustainability Report / Sustainability - an important success factor

    Bern (ots) - The BKW Group (BKW) drove forward its commitment to sustainability in the 2012 financial year. The company consistently honours its responsibility in the three areas of ecology, economy and society. Further developments in the interests of sustainability generate business opportunities. The 2012 Sustainability Report documents the following three areas ...

  • 03.07.2013 – 07:00

    BKW Italia S.p.A. / Further strengthening of commitment to hydro power segment

    Bern (ots) - BKW AG is acquiring five small hydro power plants from A2A, Italy's second largest energy supplier with headquarters in Milan. Located at various sites in Brescia province (Lombardy), the facilities have a total capacity of just under 10 MW and produce some 40 GWh of power. This acquisition represents a further strengthening of BKW's hydro power commitment ...

  • 02.07.2013 – 07:00

    BKW Pricing / Adjustment of electricity prices

    Bern (ots) - As of January 1, 2014, BKW AG will be introducing an overall realignment of its electricity prices. The main reasons for these changes are: rising grid usage and system service charges imposed by Swissgrid, the increase in compensatory feed-in remuneration and, to a lesser extent, the increase in production costs in the energy sector. The actual price increase will vary from customer to customer, depending on ...