AuRico Gold Announces its Ninth Consecutive Quarter of Record Production

Toronto (ots/PRNewswire)

Young-Davidson Reports Underground Cash Costs of $656 per Ounce and Underground Unit Costs of $41 per Tonne

AuRico Gold Inc. , ("AuRico" or the "Company") today announces preliminary third quarter production results. All amounts are in U.S. dollars unless otherwise indicated. (Results for the third quarter 2014 are estimates only and are subject to change.)

AuRico is reporting its ninth consecutive quarter of record company-wide gold production driven by record production from the cornerstone Young-Davidson mine. Period-over-period production growth is expected to continue going forward, underpinned by the ongoing ramp-up in production at the Young-Davidson mine located in northern Ontario.

To view "Company Wide Quarterly Production Growth", please click: http://files.newswire.ca/975/aurico_1014.pdf

Preliminary 2014 Third Quarter Operational Results

                                                      Q1/13    Q2/13    Q3/13    Q4/13
Young-Davidson
Gold ounces produced[2]                              28,281   29,252   30,099   33,106
     Underground cash costs per gold ounce                -        -        -     $663
     Open pit cash costs per gold ounce                $694     $716     $666     $983
Total cash costs per gold ounce[3]                     $694     $716     $666     $850
Underground mine
     Tonnes mined per day                             1,130    1,611    1,417    2,590
     Grades (g/t)                                       2.7      2.5      2.8      3.1
     Development metres                               1,941    2,445    2,620    2,986
Mill processing facility
     Tonnes processed per day                         6,466    7,017    6,747    6,969
     Grades (incl. open pit stockpile)                  1.8      1.7      1.7      2.0
     Recoveries (%)                                      86%      85%      89%      88%
El Chanate
Gold ounces produced                                 17,889   18,751   18,804   16,420
Total cash costs per gold ounce[3]                     $563     $602     $588     $615
Open pit tonnes mined per day                       106,319   98,928   87,336   98,487
Consolidated Results
Gold ounces produced[2]                              46,170   48,003   48,903   49,526
Total cash costs per gold ounce[3]                     $635     $655     $628     $771

(table cont.)

                                                      Q1/14    Q2/14    Q3/14[1]
Young-Davidson
Gold ounces produced[2]                              35,104   40,166   40,538
     Underground cash costs per gold ounce             $808     $803     $656
     Open pit cash costs per gold ounce              $1,350     $974     $923
Total cash costs per gold ounce[3]                   $1,009     $871     $723
Underground mine
     Tonnes mined per day                             2,611    3,595    3,752
     Grades (g/t)                                       2.8      3.3      3.1
     Development metres                               3,772    3,545    3,269
Mill processing facility
     Tonnes processed per day                         7,163    8,230    7,670
     Grades (incl. open pit stockpile)                  1.8      2.2      1.9
     Recoveries (%)                                      87%      88%      90%
El Chanate
Gold ounces produced                                 19,110   16,032   16,499
Total cash costs per gold ounce[3]                     $586     $618     $663
Open pit tonnes mined per day                        95,402   93,808   94,643
Consolidated Results
Gold ounces produced[2]                              54,214   56,198   57,037
Total cash costs per gold ounce[3]                     $870     $801     $706

1. Data provided for the third quarter 2014 are estimates only and subject to change.

2. Includes pre-production gold ounces from the Young-Davidson underground mine prior to the declaration of commercial production in the underground mine on October 31, 2013.

3. Represents a non-GAAP measure. See page 18 of the Company's Q2 2014 Management's Discussion & Analysis for further information. Cash costs are prior to inventory net realizable value adjustments & reversals. For Young-Davidson, gold ounces for cash costs purposes include ounces produced for 2013, and ounces sold for 2014. For El Chanate and on a consolidated basis, gold ounces for cash cost purposes include ounces sold. Pre-production ounces produced at Young-Davidson are excluded from ounces produced as these ounces were credited against capitalized project costs when sold.

"The Company is pleased to report its ninth consecutive quarter of record company-wide gold production, which builds on the successes achieved in prior quarters. We are particularly encouraged that our operation teams have delivered another strong quarter of production and demonstrated that their focus remains on quality production that drives margins, with Young-Davidson reporting a significant 17% decrease in cash costs", stated Scott Perry, President and Chief Executive Officer. He continued, "The disciplined approach to our business underpins our growing production profile, which combined with our decreasing cost profile, positions the Company for long-term, sustainable performance. We remain optimistic that in the current gold price environment, the Young-Davidson mine will be generating positive free cash flow by the end of this year."

Young-Davidson Update

- At the end of the quarter, the Young-Davidson mine achieved 557 days of
  lost time incident free operations.
- Production of 40,538 gold ounces for the quarter represented the ninth
  consecutive quarter of record gold production with the operation expected to deliver
  additional period-over-period production increases going forward as the underground
  mine ramps-up to targeted levels.
- Underground cash costs for the quarter decreased to $656 per gold ounce, an
  18% decline over the prior quarter, primarily driven by increased production, lower
  unit processing costs and lower underground unit mining costs. Total cash costs for
  the quarter, which includes the low-grade open pit stockpile, decreased by 17% to $723
  per gold ounce.
- During the quarter, underground mine productivity exceeded planned levels and
  averaged approximately 3,752 tonnes per day at grades in-line with reserve grade
  estimates. With underground productivity at approximately 94% of the year-end target,
  the operation is well positioned to achieve the year-end target of 4,000 tonnes per
  day and an ultimate productivity level of 8,000 tonnes per day at the end of 2016.
- For the third full quarter of underground commercial production, unit mining
  costs declined to approximately $41 per tonne, in-line with the year-end target of $40
  per tonne.
- During the quarter, underground development advance continued at planned
  levels with approximately 3,269 metres completed, an average of 36 metres per day. The
  Company will continue to focus on advancing underground development to best position
  the mine for sustainable, period-over-period, productivity increases in the fourth
  quarter and beyond.
- During the quarter, the mill facility averaged 7,670 tonnes per day, including
  4-days of downtime for scheduled mill reline activities. Recoveries increased over
  prior periods to a record 90%, which is expected to be sustained going forward.
- As planned, the short life open pit mine was fully depleted in early June and
  as a result, during the quarter higher grade underground mill feed was supplemented
  with low grade open pit stockpiled ore to ensure the mill processing facility was
  operating at peak capacity. The open pit stockpile will continue to supplement
  underground ore feed to the mill processing facility as the underground mine ramps up
  to targeted levels and the remaining stockpile will be processed at the end of the
  mine life.
- Currently, approximately 2.6 million tonnes of open pit ore, at an average
  grade of approximately 0.80 grams per tonne, is stockpiled ahead of the mill facility
  for future processing. As the related mining costs associated with the stockpile were
  expended in prior periods, the processing of this ore will favourably augment the
  mine's free cash flow profile going forward.

El Chanate Update

- During the quarter, the open pit mining rate averaged 94,643 tonnes per
  day with mined grades being in-line with plan.
- Mining operations in the third quarter reflected a transition from the
  sequencing of lower grade mining areas to higher grade mining areas during the latter
  part of the quarter.
- Production increased over the prior quarter while cash costs for the quarter
  were $663 per ounce, which is in-line with guidance levels.

About AuRico Gold

AuRico Gold is a leading Canadian gold producer with mines and projects in North America that have significant production growth and exploration potential. The Company is focused on its core operations including the Young-Davidson gold mine in northern Ontario, and the El Chanate mine in Sonora State, Mexico. AuRico's project pipeline also includes advanced development opportunities in Mexico and Canada. AuRico's head office is located in Toronto, Ontario, Canada.

Cautionary Statement

This press release contains forward-looking statements and forward-looking information as defined under Canadian and U.S. securities laws. All statements, other than statements of historical fact, are forward-looking statements. The words "expect", "believe", "anticipate", "will", "intend", "estimate", "forecast", "budget" and similar expressions identify forward-looking statements. Forward-looking statements include information as to strategy, plans or future financial or operating performance, such as the Company's expansion plans, project timelines, production plans, projected cash flows or capital expenditures, cost estimates, projected exploration results, reserve and resource estimates and other statements that express management's expectations or estimates of future performance. Forward-looking statements are necessarily based upon a number of factors and assumptions that, while considered reasonable by management, are inherently subject to significant uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking statements, including: uncertainty of production and cost estimates; fluctuations in the price of gold and foreign exchange rates; the uncertainty of replacing depleted reserves and the possible recalculation or reduction of reserves and resources; the risk that the Young-Davidson shaft will not perform as planned; the risk that mining operations do not meet expectations; the risk that projects will not be developed according to budgets or timelines, changes in laws in Canada, Mexico and other jurisdictions in which the Company may carry on business; risks of obtaining necessary licenses, permits or approvals for operations or projects such as Kemess; disputes over title to properties; the speculative nature of mineral exploration and development; risks related to aboriginal or Ejido title claims; compliance risks with respect to current and future environmental regulations; disruptions affecting operations; opportunities that may be pursued by the Company; employee relations; availability and costs of mining inputs and labor; the ability to secure capital to execute business plans; volatility of the Company's share price; continuation of the dividend and dividend reinvestment plan; the effect of future financings; litigation; risk of loss due to sabotage and civil disturbances; the values of assets and liabilities based on projected future cash flows; risks arising from derivative instruments or the absence of hedging; adequacy of internal control over financial reporting; changes in credit rating; and the impact of inflation. Actual results and developments are likely to differ, and may differ materially, from those expressed or implied by the forward-looking statements contained herein. Such statements are based on a number of assumptions which may prove to be incorrect, including assumptions about: business and economic conditions; commodity prices and the price of key inputs such as labour, fuel and electricity; credit market conditions and conditions in financial markets generally; revenue and cash flow estimates, production levels, development schedules and the associated costs; ability to procure equipment and supplies and ability to do so on a timely basis; the timing of the receipt of permits and other approvals for projects and operations; the ability to attract and retain skilled employees and contractors for the operations; the accuracy of reserve and resource estimates; the impact of changes in currency exchange rates on costs and results; interest rates; taxation; and ongoing relations with employees and business partners. The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable law.

PDF available at: http://stream1.newswire.ca/media/2014/10/14/20141014_C7501_DOC_EN_43002.pdf

For further information:

For further information please visit the AuRico Gold website at http://www.auricogold.com or contact:

Scott Perry
President and Chief Executive Officer
AuRico Gold Inc.
+1-647-260-8880

Anne Day
Vice President, Investor Relations and Communications
AuRico Gold Inc.
+1-647-260-8880

(AUQ. AUQ)

Weitere Storys: AuRico Gold Inc.
Weitere Storys: AuRico Gold Inc.
  • 06.10.2014 – 22:42

    AuRico Gold Announces Details for Third Quarter Results

    Toronto (ots/PRNewswire) - AuRico Gold Inc. , ("AuRico" or the "Company") today announced that it will release the Company's third quarter financial results for the period ended September 30, 2014 after market close on Thursday, November 6, 2014. The financial statements will be available on the Company's website at http://www.auricogold.com or http://www.sedar.com. Webcast and Conference Call A webcast and conference ...

  • 18.09.2014 – 18:56

    AuRico Gold Appoints Janice Stairs, LLB, MBA to the Board of Directors

    Toronto (ots/PRNewswire) - AuRico Gold Inc. , ("AuRico" or the "Company") AuRico is pleased to announce the appointment of Janice Stairs, LLB, MBA to the Board of Directors of the Company. Ms. Stairs has over 25 years of experience in senior management and senior advisory roles with public and private companies involved in the natural resource and other sectors. Ms. ...