Binder+Co receives three new, major orders from South Africa, the USA and Portugal

Gleisdorf (euro adhoc) -

  ots.CorporateNews transmitted by euro adhoc. The issuer is responsible for
  the content of this announcement.
companies
Gleisdorf, April 1, 2009. The Styrian
mechanical engineering and plant building company Binder+Co recently 
received three major contracts in the Environmental Technology 
Segment, which represent a notable success in the face of the current
crisis. These orders mean that the order backlog of EUR 32.99 million
carried over into the current business year has now been increased by
a further EUR 8.0 million.
Used glass recycling system for South Africa represents one of the 
largest environmental technology orders in company history The newly 
founded Nampak Wiegand Glass company (a joint venture between the 
listed South African company, Nampak Ltd., and the German enterprise 
Wiegand Glas) has commissioned Binder+Co with the construction of a 
complete used glass processing facility at its glassworks in 
Roodekop, South Africa. The works produces container glass using 
three melting ends and three production lines. The ordered sorting 
plant is to initially handle 24 tons of glass per hour and when fully
completed, 36 tons per hour.
For Binder+Co, this contract constitutes one of the largest orders 
ever received in the Environmental Technology Segment and also means 
that the Styrian company now covers the entire glass recycling market
in southern Africa.
Major US contract represents the first used glass recycling 
technology order from a brewery With its newly founded subsidiary, 
Ripple Glass, the Boulvard Brewing Co. brewery is now to enter the 
glass recycling field. The aim is employ used glass for the 
production of high-purity glass meal, which will be utilised by the 
insulation materials industry. Binder+Co prepared a design concept 
for the new plant in Kansas City, Missouri, supplies the core 
components and assists the brewery with its know-how and experience. 
Plant start-up is planned for the end of 2009 and the sorting system 
will handle 5 tons of glass per hour.
This order not only represents a massive vote of confidence in 
Binder+Co´s technology by the customer, but is especially pleasing in
view of the current economic situation in the USA.
Binder+Co´s supply of two recycling plants in Portugal provides a 
reference in the plastics recycling field Among other items, with the
delivery of its CRITERION sorting system, Binder+Co is to supply the 
key sections of two new plastics recycling plants in Portugal. The 
plants, which are operated by the ALGAR Recycling company, are 
located in the Algarve. They are scheduled to commence operations at 
the end of 2009 and will handle approximately 3 tons of packaging 
waste per hour.
In addition to the successful developments in the glass sector, this 
order provides Binder+Co with a new reference in the plastics 
recycling field.
end of announcement                               euro adhoc

Further inquiry note:

Karl Grabner, Member of the Management Board
Telephone +43/3112/800-363

Branche: Machine Manufacturing
ISIN: AT000BINDER3
WKN:
Index: mid market
Börsen: Wiener Börse AG / Regulated free trade

Plus de actualités: Binder+Co Aktiengesellschaft
Plus de actualités: Binder+Co Aktiengesellschaft