BKW Energie AG

Transmission network costs and tariffs for 2009
BKW lodges appeal with Federal Court - definitive legal clarity required

10.01.2011 – 18:00

Bern (ots)

BKW FMB Energy Ltd (BKW) has lodged an appeal with
the Federal Court against the decision of the Federal  Administrative
Court dated 11 November 2010 upholding a ruling by the Federal 
Electricity Commission (ElCom) which decreed a reduction in the 
chargeable costs for the transmission network (Level 1).
The ElCom decree upheld by the Federal Administrative Court 
stipulates a reduction of around CHF 10 million in BKW's chargeable 
network costs (Network Level 1) for 2009. BKW is lodging the appeal 
in order to have the ruling reviewed and obtain definitive 
clarification from the Federal Court.